Increase Verification Rate

Applicants upload three documents in the Best Egg loan application and can now see each one’s status instead of calling to ask.

Outcome

71%

Verification rate in the live A/B test, against 61% for control. Sized at 7,000 fewer support calls a month

Step 1: Action required. Complete the following action items to finish your application. Thank you screen confirming documents were submitted, with a 3 of 3 documents checklist
Role
Sr. Director of Product Design
Team
1 senior product designer, 1 product designer
Timeline
3 months
Scope
Discovery to live A/B test

The problem

Once a file was sent, the dashboard went quiet, so applicants called to ask.

  • Unclear statusAfter submitting, applicants couldn’t tell what was pending, accepted or still needed.
  • Accepted formatsThe dashboard didn’t say which formats or alternatives were accepted.
  • Progress bar confusionA multi-step progress bar implied steps that didn’t exist, right at the point of submission.
Application pending dashboard with Step 1: Action Required, asking a co-owner to sign a document

Research

From the usability sessions on the current upload flow.

“If that ‘in review’ would’ve been maybe bigger or a different color, I would’ve noticed it earlier.”

Clear status badgeUsability session Best Egg

“Maybe just telling me how I will hear from you would make me feel more confident and informed.”

CommunicationUsability session Best Egg

“Instead of that little circle, there could be a button called upload for each individual W2, pay stub, and ID.”

Visual cuesUsability session Best Egg

How I led it

Requirements

I got product, engineering, compliance and operations to agree on requirements before design started, and kept the priorities from shifting once it had.

Usability tests

With the insights team, we ran A/B usability tests of the current upload flow (Design A) against the document-led design (Design B). The senior product designer and product designer turned the findings into a prioritized list of changes, each tied to a KPI.

Direction

I set the design strategy and directed a senior product designer and a product designer from discovery through the A/B test, with weekly reviews to hold quality across parallel streams.

Key decisions

A checklist replaced the progress bar

Design B is a document-led checklist: one clear upload per document, explicit format guidance and a status the applicant can see the moment a file lands.

A clear end to the upload

We saw applicants stall after adding their documents: nothing told them they were done. We added an “I’m done” button that takes them back to the dashboard, and applicants stopped stalling.

The uploaded files card: two documents marked In review, then an Upload another button and a filled I'm done button

Results

The opportunity, 7,000 fewer support calls a month, was sized with product and operations before the work began.

71%
verification rate with Design B in the live A/B test, against 61% for control
Live A/B test · Design B vs control
MetricDesign A (current)Design B (document-led)
All 3 documents uploadedSome applicants dropped off100% completion rate
First impression clarityPositive, but the progress bar confused applicantsApplicants kept pointing to the clear status indicators
Upload confidenceUnsure after submittingConfident the upload was accepted
Customer support riskQuestions about status, format, timelineFewer open questions, most answered on the page
Direct Pay confusionYes, not clear in the verification flowResolved by separating it from the upload steps
  • RolloutDesign B shipped to production and is now live in an A/B test, ramped to 50% of applicants. As of September 30, 2024, its verification rate is 71%, against 61% for control.